Quality & Commissioning Process

Reliable Processes - Predictable Outcomes - Repeatable Results

Level 0

  • Design stage
  • Basis of Design is developed
  • Specifications for systems and equipment are developed
  • Design Review
  • Procurement
  • IFC Drawings are issued

Level 1

  • Factory Acceptance Testing
  • Factory Witness Testing
  • Client Team is presented with the systems/equipment which will be delivered to the project site
  • Factory Testing is conducted and witnessed and signed off as ready to dispatch

Level 2A

  • Delivery Verification
  • Vendors/Contractors take receipt of their systems and equipment
  • Initial inspection that no damage has been caused during transport to site

Level 2B

  • Construction is complete 
  • All Static and Dead Testing has been completed and witnessed
  • Documentation and test reports are completed and uploaded to the project repository and linked to the appropriate Level 2B Tag 
  • Upon review and sign off by the appointed Design and Commissioning Consultants. energization is requested

Energization Process

  • Bespoke Digital Energization Process
  • Upon Level 2B Tag achievement, the Vendor/Contractor requests energization of the system/equipment 
  • This is a transparent process where all stakeholders have visibility of what will be energized

Level 3

  • Site Acceptance Testing
  • Vendor/Contractor conduct testing against the SOO

Level 4

  • Functional Performance Testing
  • CxA executes the FPT to validate the design intent has been met and all systems operate as per the SOO

Level 5

  • Integrated Systems Testing
  • CxA executes the IST to validate that all critical systems are functioning as per the design

Level 6

  • Handover to Operations Team
  • The Cx Team officially sign off the facility as Ready for Service
  • Training takes place for the Operations Team to familiarise themselves with all systems and equipment
  • The Operations Team takes receipt of the facility and verifies that all systems are in auto with no alarms

  • Privacy Policy

Corey Engineering Limited

Loughville, Ennis, Co. Clare, Ireland

+353 (0)87 4161671

Copyright © 2025 Corey Engineering - All Rights Reserved.

Powered by

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

DeclineAccept